In the first picture you can see how far down they have dug by the sandstone "cliff" that remains on the right. It was encouraging to see so many people working on it. The foreman said they were on schedule and would be working all through January. He was just doing the external building work and he expected the shell to be finished in about July 2014. However the entire construction would not be finished until 2015.
The second photograph shows the southern end of the property, where they have not yet started construction on the building itself, although the retaining walls are built. This part of the building will have only 5 storeys, while the northern end will be 10 storeys.